Planyard projects overview and budget columns explained

Written By Ekke

Last updated 9 days ago

The budget overview brings together all key financial indicators of your project in one view. This article explains the terms used in two places in Planyard: the projects overview summary and the budget table.

Both answer the same four questions: what should it cost, what will we earn, what are we spending, and where will we end up?

Column descriptions in Planyard: in the budget, hover over the ? icon next to any column title. A tooltip explains what the column shows, without leaving the budget view.

1. Budget: what should the project cost?

Term

Meaning

Net estimated cost

The cost estimated when the job was priced. The starting point.

Target budget

Internal goal. It can be set below the estimated cost so the team buys smarter, or kept equal to the net estimated cost to simplify the process.

Revised Budget

The project manager's forecast of the final cost. It starts equal to the target budget and can change through manual edits.
For example, if committed or approved costs have gone over a target, the budget has to be revised. Target budget stays with original numbers and revised budget value will be updated.

Budget variance

Target budget − revised budget = budget variance.
Values in red (negative) = forecast is worse than the goal;
Values in green = better than planned.

2. Income: what will the client pay us?

Term

Meaning

Budget submitted to client / Client budget

Price quoted to the client (your estimate + added markup). It represents the expected income from the item.

Committed income

The value of client contracts created in Planyard. If you have multiple contracts for the same budget item, the column shows the total of all contracts.

Approved sales invoices / Approved income

The total value of sales invoices that have been processed and assigned to this budget item. This gives you an overview of sales to date.

Remaining income

Committed income − approved income: still to bill

3. Costs: what are we spending?

Term

Meaning

Committed costs

Value of everything ordered: subcontracts, purchase orders, standalone invoices. This shows how much you have committed financially to date, regardless of whether payments have been made.

Committed variations

The part of committed costs that comes from changes to subcontracts and purchase orders.

In subcontracts

Value of subcontracts only

In payment applications

Approved subcontractor claims

Approved costs

Costs actually booked or paid (approved invoices and claims)

Remaining budget / Uncommitted costs

Revised budget − committed costs: forecast cost not yet ordered

Remaining costs

Revised budget − approved costs: still to be spent

4. Total: where will we end up?

Term

Meaning

Profitability forecast

Budget submitted to client − revised budget: expected profit or loss.

Margin

Profitability forecast ÷ client budget, shown as a percentage.

It tells how much of every euro earned stays as profit, so projects of different sizes can be compared.

Cashflow

Approved income − approved costs: cash position to date. 

It compares what has been billed to the client with the costs booked so far. A negative value means costs are running ahead of billing, so the company is financing the project itself.

Remaining cashflow

Remaining income − remaining costs: cash still to come.

It shows whether the rest of the project will bring in more money than it still needs to spend.

Tip: read budget variance and profitability forecast together to spot risks early. Budget variance shows how well the team is buying against its own internal targets. Profitability forecast shows what that means for the margin on the client contract. A red variance with a healthy forecast is an internal warning; a falling forecast means the project’s profit itself is at risk.