Forecast and control costs

How to add contingency to your estimates and budget

Written By Mirell

Last updated 9 days ago

Contingency (also called a risk allowance) is money set aside for unexpected costs. The best time to add it is during estimating, as a percentage per item and material. If you didn't use the cost estimating tool, you can add contingency later as a dedicated line in your project budget.

Add contingency to already to your estimates

In the cost estimating tool, you can add a contingency percentage to each item and material.

Turn on estimate contingency

Estimate contingency is available on the Essentials, Professional and Ultimate plans, but not on the Estimating plan. An administrator needs to turn the setting on for your company first:

  1. Go to Company Settings → Estimation Settings.

  2. Enable Estimate contingency.

Add contingency percentages

Once the setting is on, you can add a contingency percentage per item and per material in your estimate. Planyard shows the contingency at both levels, so you can see how much risk allowance each item and material carries.

Show or hide contingency in exports

When you export an estimate to PDF or Excel, use the contingency checkbox in the export dialog to choose whether the contingency column is included. For example, you can keep it in your internal copy and leave it out of the version you send to the client.

Add contingency to your existing project budget

If you didn't add contingency during estimating, create a dedicated contingency line under your cost headings:

  1. In the Budget view, click Add line-item in the top-right corner.

  2. Select Custom.

  3. Name the line, for example Contingency or Risk allowance, and choose the cost heading it belongs under.

  4. Click Create, then add the amount you're setting aside.

Use the contingency when risks occur

When an unexpected cost comes up, you have two options:

  • Assign the cost to the contingency line. Book the unexpected cost directly against it.

  • Move funds to the affected line. Lower the contingency line's revised budget and raise the revised budget of the line where the cost occurred by the same amount.

Tip: moving funds keeps each cost on the line where it belongs, so you can see later which packages needed extra money.