How to process stand alone labour cost
Written By Ekke
Last updated About 4 hours ago
You can record labour-related costs in Planyard even if they aren’t tied to a work order. The process has two main steps: locating and starting the document, then processing and tagging the cost.
1. How to navigate and start processing the invoice
- Go to Projects and open the relevant project.
- In the project menu, go to Files.
- Upload the cost document.
- After the upload, click the document to open it for processing.
2. How to process and tag the cost
- In the Company dropdown, select:
- Your own company (for internal staff)
- An external company (for hired labor)
- In the Document type dropdown, choose the Team timesheet or Work progress option.
- Fill in the general document details:
- Document name
- Invoice number (if applicable)
- Contact (if applicable)
- Tag the cost:
- Click Labor cost
- Or click Overhead cost
- Scroll down to the allocation section.
- Allocate the cost to the budget:
- Click Select in bulk to view the full budget and choose multiple items
- Or use the dropdown to select individual budget lines
- Add the value of the cost to your selected items.
Note: The option to tag as labor cost or overhead cost only appears after selecting the document type.
Was this helpful?
More in Cost management